Project Timing and Progress
Cape Coral: Everest Parkway and River Pipeline Design & Permitting June 2020 – The project is currently in the design and permitting phase.
Cape Coral – Everest Parkway: Fall 2021 – Summer 2022 (anticipated dates)
Construction of the uplands portion of the pipeline on the north side of Everest Parkway from the Everest Water Reclamation Facility to Horton Park is expected to begin in fall 2021 and anticipated to be completed in summer 2022.
River Pipeline: Fall 2021 – December 2022 (anticipated dates)
Construction of the HDD portion of the pipeline from Horton Park across the Caloosahatchee River to a connection point in Fort Myers is anticipated to begin in fall 2021, depending on permitting. The HDD portion of the project is anticipated to be complete by December 2022.
Fort Myers: TBD
Construction for the Fort Myers connection to the South Advanced Wastewater Treatment Facility is TBD.
Construction on Everest Parkway
0%
Construction of the River Pipeline
0%
Construction in Fort Myers
0%

Two cities working together to better the environment